As part of our 2008 retirement plan we intend to spend summers in our UK house and winters in our Manila house.

In 2014 we decided to demolish our Manila house garage and kitchen, in order to construct a 2 story extension comprising a new larger kitchen, additional lounge, master bedroom, office/den and second bathroom. This was completed in 2016.

 

Ground Floor Plan
Ground Floor Plan
First Floor Plan
First Floor Plan

After almost two years of hassle, sacking the first architect, and dealing with unbelievable municipality bureaucracy, we finally got the building permit issued in October 2014.

Demolition work and excavation for the new foundations started the second week of November 2014.


Before Demolition
Before Demolition
Before Demolition
Before Demolition
Start of Demolition Work. Nov 2014
Start of Demolition Work. Nov 2014
Excavation and Footings. Dec 2014
Excavation and Footings. Dec 2014
Scaffolding. Dec 2014
Scaffolding. Dec 2014
First floor ready for concrete pour. Jan 2015
First floor ready for concrete pour. Jan 2015
Preparation for roofing. Feb 2015
Preparation for roofing. Feb 2015
May 2015
May 2015
May 2015
May 2015
New Lounge May 2015
New Lounge May 2015
New Lounge May 2015
New Lounge May 2015
Staircase May 2015
Staircase May 2015
Office / Den May 2015
Office / Den May 2015
Shower Room May 2015
Shower Room May 2015
Shower Room September 2015
Shower Room September 2015
Apparent marks on wall are camera flash reflections from windows
Bedroom May 2015
Apparent marks on wall are camera flash reflections from windows
Bedroom May 2015
Kitchen in progress May 2015
Kitchen in progress May 2015
Kitchen September 2015
Kitchen September 2015
Kitchen September 2015
Kitchen September 2015

October 2015 Phase II

 

Builders are working flat out on renovating the original part of the house putting in new ceilings, floors, A/C's, and decorating.

Old Lounge Refurbishment in Progress Dec. 2015
Old Lounge Refurbishment in Progress Dec. 2015
Old Lounge Refurbishment in Progress Dec. 2015
Old Lounge Refurbishment in Progress Dec. 2015
Front of house finished Feb 2016
Front of house finished Feb 2016
Front of house finished Feb 2016
Front of house finished Feb 2016
Front of house finished Feb 2016
Front of house finished Feb 2016
Needs junk and rubble clearance and planting Mar 2016
Needs junk and rubble clearance and planting Mar 2016
Needs junk and rubble clearance and planting Mar 2016
Needs junk and rubble clearance and planting Mar 2016
Needs rubble clearance and planting Mar 2016
Needs rubble clearance and planting Mar 2016
New Lounge June 2016
New Lounge June 2016
New Lounge June 2016
New Lounge June 2016
New Lounge June 2016
New Lounge June 2016
Old Lounge June 2016
Old Lounge June 2016
Old Lounge June 2016
Old Lounge June 2016
Kitchen June 2016
Kitchen June 2016
Kitchen June 2016
Kitchen June 2016
Office / Den June 2016
Office / Den June 2016
Office / Den June 2016
Office / Den June 2016
Master Bedroom June 2016
Master Bedroom June 2016
Master Bedroom June 2016
Master Bedroom June 2016
June 2016
June 2016
June 2016
June 2016
June 2016
June 2016
June 2016
June 2016
June 2016
June 2016

House Warming Parties 2 & 3 July 2016

Garden and Patio photos December 2016

NEW PHOTOS OF GARDEN 2020